Mitsubishi Power to supply 340MW gas turbines for Meranti Power's Jurong power plant

The M701F-series gas turbines would increase the facility's electricity production.

Mitsubishi Power will design and manufacture two 340MW M701F-series open-cycle gas turbines (OCGTs) for Meranti Power's  facility at Jurong Island as part of a consortium with Jurong Engineering Limited.

The gas turbines can operate with a 30% hydrogen fuel mix and configure for a 100% hydrogen firing in the future.

Once installed, the OCGTs will ramp up the power facility's power production to deliver electricity on demand, minimize the risk of energy disruption, and enhance the country's overall grid stability.

READ MORE: Sembcorp to build $900m multi-utilities centre in Jurong Island

The OCGT power facility at Jurong Island will be in commercial operation by mid-2025.

Join Singapore Business Review community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!